We use advanced technological solutions in harmony with high quality concrete products equipment, processes and skills, to bring quality up and total cost of project down for Australian government, developers and builders.
Lilydale Airport was in desperate need of an upgrade and repairs to an existing grass taxi-way due to flooding issues. The catch – they needed repairs done in two weeks. Read more…
Sydney Airport - Taxiway A16 Slab Replacement Project, August 2016
Site management
Saw cutting
Demolition
Dowell drilling
13 full depth slab replacements
Volumetric batching and placement 130m³ of CTS Rapid Set Concrete.
VicRoads Keilor Park Drive - Slab replacement, June 2016
Site Management
Materials delivery and management
Saw Cutting
Demolition of damaged pavement
Dowelling and installation of steel mesh
14 pavement slab replaced
Volumetric batching and placement of 70m³ CTS Rapid Set Concrete